Friday, July 20, 2012

This past week A. Lamp Concrete Contractors completed concrete removal and replacement along Grove Street, Barry Lane, LaFontaine Drive, Charlie Court, Manu Court, Burnham Court, Wedgwood Drive, and Simonsen Lane. Arrow Road Construction also performed pavement removal along Grove Street and Pine Street.

Next week A. Lamp will be performing concrete curb & gutter repairs along Wilmette Avenue, Sheffield Lane, Hawthorn Lane, and Elizabeth Lane. The contractor will also perform concrete base repairs along Grove Street and Pine Street. Residents will be notified prior to concrete work starting and if your driveway access will be restricted.   

Next week Arrow Road Construction will begin existing pavement removal at various locations throughout the Village. Residents will be notified prior to this work starting.  Parking on the streets will be restricted during the pavement removal process.

During the duration of the project, access to driveways may be limited due to work being performed. We will try to give as much notice as possible when this will occur. Thank You for your patience and understanding during these times.