Friday, July 27, 2012

This past week A. Lamp Concrete Contractors completed concrete removal and replacement along Wilmette Avenue, Sheffield Lane, Hawthorne Lane, Elizabeth Lane, Maplewood Lane, Sleepy Hollow Road, Stevens Drive, and Grove Street.

Next week A. Lamp will be performing concrete curb & gutter repairs along Maplewood Lane, Sleepy Hollow Road, Stevens Drive, Riverside Court, and Swainewood Drive. Residents will be notified prior to concrete work starting and if your driveway access will be restricted.   

Next week Arrow Road Construction will begin existing pavement removal along Charlie Court, Manu Court, Barry Lane, LaFontaine Drive, Joanne Drive, Elmdale Avenue, Pickwick Lane, Simonsen Lane, Rolling Pass, Crowne Lane, Executive Lane, Burnham Court, and Wedgewood Avenue. Residents will be notified prior to this work starting.  Parking on the streets will be restricted during the pavement removal process.

During the duration of the project, access to driveways may be limited due to work being performed. We will try to give as much notice as possible when this will occur. Thank You for your patience and understanding during these times.