Friday, August 3, 2012

This past week A. Lamp Concrete Contractors completed concrete removal and replacement along Maplewood Lane, Sleepy Hollow Road, Stevens Drive, Riverside Court, and Swainewood Drive. The concrete curb & gutter removal and replacements is 90% complete at this time with miscellaneous areas yet to be completed.

This past week Arrow Road Construction performed pavement removal along Charlie Court, Manu Court, Joanne Drive, Elmdale Avenue, and Pickwick Lane.

Next week Arrow Road Construction will continue to remove the existing pavement along various roadways within the Village. Residents will be notified prior to this work starting.  Parking on the streets will be restricted during the pavement removal process.

Arrow Road Construction will begin asphalt paving along Grove Street, Pine Street, Charlie Court, Manu Court, Joanne Drive, Elmdale Avenue, and Pickwick Lane. Parking on the streets will again be restricted during the paving process.