Saturday, August 18, 2012

This past week Arrow Road Construction performed limited work due to weather conditions. Please be assured, the Village is doing everything possible to ensure the project is completed in a timely manner and limit the inconvenience to the residents.

The following is the contractor’s work schedule for next week, depending on weather condition:

Monday, August 20th: Asphalt paving on Joanne Drive, Elmdale Avenue, and Pickwick Avenue. Pavement Removal along Elm Street.
Tuesday, August 21st: Asphalt paving on Westview Lane, West Lake Frontage Road, Rolling Pass, Burnham Court, Wedgewood Court, and Simonsen Lane. Pavement removal along Birchwood Court, Elm Street, Long Valley, and Harrison. Grading on Elm Street
Wednesday, August 22nd: Grading along Elm Street
Thursday, August 23rd: Paving along Elm Street and Birchwood Court. Pavement removal along Stevens Drive, Mapplewood Lane, Sheffield Lane, Hawthorn Lane, and Elizabeth Lane.

Parking along the street will be restricted during all roadway work including paving, grading, and pavement removal. Residents will be notified of parking restrictions.

Thank you in advance for your patience and cooperation during the roadway resurfacing project.